In brief
- In the US and Canada the bill is candid: demand and reactive power are line items of their own, so poor power factor is billed twice, in demand and as a penalty.
- Many Ontario distributors bill demand on the greater of kW or 90% of kVA: at power factor 0.80 an 800 kW site is billed for 900, at 0.90 for 800.
- A data-centre surge is tightening grid capacity: PJM's capacity price rose roughly ten-fold in two years, so the 184 kVA a corrected 800 kW site frees is now worth having.
- HarmoniQ's saving falls on three invoice lines: 10–20% fewer kWh, power-factor penalties eliminated and capacity charges reduced, up to 25% off the total bill where all three apply.
Pull up an industrial electricity bill in much of Africa or South Asia and the real cost of power is hidden: in diesel, in downtime, in damaged motors that never appear as a line item. North America is the opposite. Here the bill is candid. It tells an operator, in dollars and cents, what poor power factor and a spiky load profile are costing, because demand and reactive power are printed on the invoice as charges of their own.
That candour is the story. The United States and Canada run comparatively reliable grids, so the case for power quality is not led by keeping the lights on. It is led by the bill: a demand charge that can rival the energy charge for size, and a reactive-power penalty that applies the moment power factor drifts below a threshold the utility has written down. Poor power factor inflates the first and triggers the second, and both respond directly to correction at the switchboard.
A second force is reshaping the picture. An AI and electrification demand surge, data centres above all, is tightening grid capacity across both countries for the first time in a generation. Where spare capacity was once assumed, it is now scarce and valuable, and the headroom freed inside an existing building turns from an engineering nicety into deferred capital. This article follows both threads across the United States and Canada: the billed cost of bad power, and the rising worth of freed capacity.
01Your power factor is on your bill
The defining feature of a North American industrial electricity bill is that it is rarely a single number multiplied by kilowatt-hours. For a commercial or industrial account, the energy charge is only part of the total. Alongside it sits the demand charge: a separate fee based on the highest rate of power draw, in kilowatts, recorded in any short interval of the billing period. One fifteen-minute spike can set the demand charge for the whole month.
This is where power factor stops being abstract. On many tariffs the billed demand is not simply the metered kilowatts: it is the kilowatts divided by the power factor, which in effect bills the apparent power (kVA) the utility's network has to carry. A site drawing 800 kW at a power factor of 0.80 is billed for 1,000 kVA. On top of that, many utilities levy a direct reactive-power charge whenever power factor falls below a threshold set in the tariff.
The pointPoor power factor is charged twice: once by inflating billed demand, and again as an explicit penalty.
There is no single national electricity regulator in either country. In the United States, rates and demand-charge structures are set utility by utility and state by state; in Canada, province by province. The mechanism holds even where the numbers do not. Where the bill separates demand and reactive power from energy, correcting power factor cuts it directly, independent of the energy rate and without changing a single unit of production.
02One continent, two countries, many tariffs
Neither "the United States" nor "Canada" is a single power market. The US Energy Information Administration puts the national average commercial rate at roughly US$0.13/kWh, but that average conceals a wide spread: California and much of the Northeast pay well above it, the Southeast and Texas below it. Canada's range is just as wide, set by each province's generation mix and published in each provincial utility's rate schedules. Exhibit 1 summarises the markets in scope.
| Market | Commercial rate | What drives the bill | Lead lever |
|---|---|---|---|
| US · California and Northeast | Well above the national average | A high energy rate, plus demand billed on kW ÷ PF | Demand and energy |
| US · national average | About US$0.13/kWh (EIA) | Demand charges and kVAR penalties weigh heavily | Demand and the reactive penalty |
| US · Southeast and Texas | Below the national average | A low energy rate; demand charges and capacity still bite | Demand and capacity |
| Canada · Ontario | Mid-range | Demand billed on the greater of kW or 90% of kVA; Global Adjustment peaks | Reactive (kVA) and peak demand |
| Canada · Alberta | Volatile, market-priced | Market price swings, and a fast-filling data-centre queue tightening capacity | Demand and capacity |
| Canada · Quebec, BC, Manitoba | Low, hydro-based | Cheap hydro makes the energy rate a weak savings lever | Capacity and harmonics |
| Canada · Nova Scotia | High | An expensive grid where every billed kVA counts | Demand and the reactive penalty |
What counts as industrial here
The heaviest North American loads sit on medium- and high-voltage connections, outside the scope of low-voltage power-quality equipment: aluminium smelting, oil refining, large pulp and paper mills. The opportunity this article describes is the broad low-voltage base: light and medium manufacturing, much of it reshoring; commercial real estate and offices; big-box and general retail; healthcare; cold chain and food and beverage logistics; hotels; school and university campuses; water and wastewater; and airports. These are the sites where correction at the switchboard goes to work.
Two patterns cut across the table. First, in the higher-rate markets of California, the Northeast and Nova Scotia, the energy charge is large enough that energy savings and reactive correction carry real weight on their own. Second, in the cheap-hydro provinces of Quebec, British Columbia and Manitoba, the energy rate is a weak lever, so the value shifts to freeing capacity and meeting harmonic standards. Ontario sits in a category of its own, for reasons worth a closer look.
03Ontario's kVA rule and the Global Adjustment
Ontario offers the clearest illustration on the continent of power factor as a direct monthly charge. Many Ontario distributors, under rates approved by the Ontario Energy Board, bill demand on the greater of metered kW or 90% of metered kVA. The mechanism is deliberate. Once a site's power factor falls below 0.90, the 90%-of-kVA figure overtakes the real-power figure, and the customer is billed on apparent power rather than on the work actually done. Low power factor is not a hidden inefficiency in Ontario. It is a number that appears, every month, on the demand line.
| Power factor | Apparent power | 90% of kVA | Billed demand | kVA freed |
|---|---|---|---|---|
| 0.80 | 1,000 kVA | 900 | 900, set by kVA | — |
| 0.90 | 889 kVA | 800 | 800, set by kW | 111 kVA |
| 0.98 | 816 kVA | 735 | 800, set by kW | 184 kVA |
The table makes two points. On Ontario's demand line, correction pays up to 0.90 and no further: from there the bill is set by real kilowatts. The connection keeps gaining, though. At 0.98 the same 800 kW needs 184 kVA less than it did at 0.80, and on tariffs that bill kVA outright, or charge for reactive power against a tighter threshold, that difference is money as well as headroom.
Layered on top is the Global Adjustment. Under the Independent Electricity System Operator's Industrial Conservation Initiative, the largest consumers' share of it is set by their demand during the province's five highest peak hours of the year. A facility that holds its load down through those coincident peaks pays far less; one that spikes through them pays more. It is one of the strongest peak-demand signals anywhere in North America.
Two charges, one root cause
In Ontario the same underlying behaviour, an uncorrected and peaky load, is penalised through two channels: a demand charge billed on apparent power whenever power factor sags, and a Global Adjustment share driven by demand in a handful of system peaks. Correction takes the first off the demand line outright. The second rewards anything that lowers real demand in those few hours, and the losses a cleaner current no longer creates count there too. The physics is ordinary; what makes Ontario instructive is how plainly the tariff puts a price on it.
The pointThe lesson generalises beyond Ontario. Wherever a tariff bills on kVA, applies a reactive-energy penalty or allocates cost by coincident peak, the utility has already quantified the bad-power problem and printed it on the invoice. The operator's task is not to discover a hidden cost. It is to remove one that is already itemised.
04The data-centre surge and the vanishing of spare capacity
For more than a decade, US electricity demand was essentially flat. That era has ended. AI and data-centre build-out, manufacturing reshoring, and the electrification of transport and heating have put load growth back on the system at a pace utilities have not planned for in a generation.
The clearest market signal is in capacity prices. PJM Interconnection coordinates the grid across the Mid-Atlantic and parts of the Midwest, and its own auction results show the capacity clearing price rising roughly ten-fold over two years, as the value of firm capacity caught up with how scarce it had become. Canada feels the same pressure regionally: the Alberta Electric System Operator has reported more than 10 GW of data-centre projects in its connection queue.
For years, spare grid capacity in North America was assumed. The AI demand surge has made it scarce, and scarce capacity is valuable capacity.
That reframes the second value lever. Reactive current and harmonic distortion lock up part of every transformer and switchboard: rating that carries current but does no useful work. Exhibit 2's site shows the scale. At a power factor of 0.80 its 800 kW loads the connection with 1,000 kVA; at 0.98 the same 800 kW needs 816 kVA, leaving 184 kVA free, and cancelling harmonic current frees more again. In a flat-demand world that headroom was a curiosity. In a capacity-constrained one it is deferred capital: room for a growing site to add load, a new production line or an EV-charging bank without triggering a service upgrade and the months-long interconnection wait that now comes with it.
- PJM's capacity clearing price over two years, roughly, by its auctions
- 10×
- Data-centre projects in Alberta's connection queue, by AESO
- 10+ GW
- Connection freed when Exhibit 2's 800 kW site goes from 0.80 to 0.98
- 184 kVA
05Harmonics, IEEE 519 and the cost of connecting
The same loads driving the bill also distort the waveform. Variable-speed drives, electronic power supplies, LED lighting, EV chargers and the inverters behind on-site solar and storage are all non-linear: they draw current in pulses that distort the clean 60 Hz sine wave the network expects. The result is harmonic distortion, which means extra heating in transformers and conductors, nuisance tripping, and faster ageing of the equipment a site depends on.
North America's common reference is IEEE 519, the standard for harmonic control in electric power systems, increasingly written into utility interconnection requirements as a condition of connecting non-linear load or embedded generation. In Canada, CSA standards play the same role alongside it. As drives, chargers and inverters multiply on commercial and industrial sites, holding distortion within those limits calls for correction that tracks the load as it changes, rather than a one-off survey or a passive trap tuned for yesterday's load.
| Value lever | High-rate markets: California, Northeast, Nova Scotia | Cheap-hydro provinces: Quebec, BC, Manitoba |
|---|---|---|
| Demand-charge reduction | Lead: a large share of the bill, where demand is billed on kVA | Strong: billed even where energy is cheap |
| Reactive-penalty removal | Lead: billed kVA and kVAR charges | Strong where kVA billing applies |
| Energy savings | Strong: a high rate per kWh | Modest: the hydro rate is low |
| Capacity freed | Rising: defers service upgrades | Lead: the main growth enabler |
| Harmonics and equipment life | Strong: IEEE 519 at interconnection | Strong: IEEE 519 and CSA |
06What it means for industrial operators
For an operator in the United States or Canada, the order in which the gains from power quality arrive is the inverse of the weak-grid world. The grid is comparatively reliable, so reliability is not the headline; the bill is. Demand-charge reduction and reactive-penalty removal lead. Freed capacity is the rising second lever, lifted by the data-centre surge. Longer equipment life rides alongside, valuable but rarely the reason a project starts.
Where HarmoniQ fits
HarmoniQ's units are shunt-connected on the low-voltage network, in parallel with the load and never in the supply path, and they go in with zero disruption. Each works where it sits.
At the load
HarmoniQ Alpha
Fitted at each machine, it cleans the current where it is drawn, so every cable upstream carries less of it and runs cooler.
At the drives
HarmoniQ Delta
Fitted at the drives panel, it cleans the current where the drives distort it, before it spreads to the feeder, busbar and transformer.
At the incomer
HarmoniQ Sigma
At the main switchgear, it corrects reactive current where the network meets the grid, so the supply and the meter see cleaner current.
With reactive current corrected and harmonics cancelled, power factor reaches 0.98+, which on a North American tariff means fewer billed kVA, no reactive-power charge and transformer capacity freed.
The lever that maps onto the invoice
On a North American bill, better power factor is not an abstraction. It is a smaller number on the demand line and the disappearance of the reactive-power charge. Because demand is so often billed on kW ÷ PF or on a share of kVA, lifting power factor from 0.80 towards unity cuts billed demand directly, before a single kilowatt-hour of consumption changes. Where capacity is tight, the same correction frees headroom on the existing connection, so a growing site can add load and defer the service upgrade.
Those are two of the three invoice lines a HarmoniQ saving falls on. The third is the energy charge itself, and Exhibit 4 sets all three against a North American bill.
| Invoice line | Where it sits on the bill | What correction does |
|---|---|---|
| Energy | The energy charge, per kWh | 10–20% fewer kWh for the same output: the line the guarantee is written against |
| Power-factor penalties | The kVAR or power-factor charge | Eliminated where the utility levies them, with power factor corrected to 0.98+ |
| Capacity charges | Demand billed on kVA or on kW ÷ PF | Reduced, because correction frees apparent power |
Together they come to up to 25% off the total electricity bill: about 25% where all three apply, and close to the energy saving alone where a tariff carries no reactive or kVA-based charge.
Our minimum performance guarantees are written against kilowatt-hours at the customer's own meter, and the units can be switched on and off so the difference shows in metered results in real time. In a market where the bill itemises the problem, the meter is also where the solution is verified: the same instrument that prices bad power confirms its removal.
North America's industrial power problem is not that the grid fails. It is that the grid charges, plainly and precisely, for power factor and peak demand, and that for the first time in a generation the spare capacity inside a building is worth freeing. What an operator cannot control is the surge tightening the grid around them. What they can control is how much of their own connection is spent on reactive current and distortion, and how much of their bill is paying for it.
Sources
- U.S. Energy Information Administration, Electric Power Monthly: average retail prices by sector and state.
- IEEE Std 519-2022, IEEE Standard for Harmonic Control in Electric Power Systems.
- PJM Interconnection, Base Residual Auction results, 2024–2025.
- Ontario Energy Board rate handbooks and distributor tariff schedules; Independent Electricity System Operator, Global Adjustment and Industrial Conservation Initiative documentation.
- Alberta Electric System Operator, connection-queue reporting on data-centre interest, 2025.
- Provincial utilities' published commercial rate schedules: Hydro-Québec, BC Hydro, Manitoba Hydro, Nova Scotia Power.
- CSA Group standards for power quality, applied alongside IEEE 519 in Canada.
Figures are indicative of conditions in 2025–2026. Rates, demand-charge structures and reactive-power penalties vary by utility and province and change over time; verify any figure with the relevant regulator or utility before relying on it.



