In brief
- Since 1 November 2025, ZESCO bills maximum-demand customers from 16 to 5,000 kVA on energy alone: K2.20 to K2.50 per kWh before VAT and excise, about $0.111 to $0.126.
- There is no longer a kVA demand charge or a fixed charge, so on the grid bill the saving runs through the energy line; confirm with ZESCO whether a power-factor requirement applies to your connection.
- Generation fell short of demand by 728.59 MW on average in 2025, the regulator reports, so load-shedding pushed sites onto diesel generators and inverter-based solar and batteries.
- HarmoniQ’s saving here is the energy line: 10–20% fewer kWh, proven at your own meter, with power factor at 0.98 or better and equipment that lasts 2–4× longer.
Drought on Lake Kariba and a grid that fell well short of demand through 2025 forced commercial and industrial sites onto diesel backup during load-shedding. Here is what power actually costs in Zambia, how the bill breaks down, and how power factor correction and harmonic filtering cut fuel burn and free backup capacity at sites from agri-processing plants to retail centres and telecom hubs.
01Energy-only grid power: until you count the diesel
ZESCO, Zambia’s state-owned, vertically integrated utility, supplies commercial and industrial customers on national tariffs approved by the Energy Regulation Board (ERB). Since 1 November 2025, its maximum-demand customers, from 16 to 5,000 kVA, pay for energy alone: K2.20 per kWh on MD1, K2.30 on MD2 and K2.50 on MD3, about $0.111 to $0.126, before VAT and excise duty. With no demand or fixed charge left, the whole grid bill now moves with the kWh.
That is only the grid bill. Through the drought, load-shedding forced sites to bridge long outages on diesel generators, at a cost per kWh well above the grid rate, and on captive solar and batteries. The real price of a kilowatt-hour in Zambia is not only what ZESCO charges; it is also what it costs to keep the site running when ZESCO cannot. Every percentage point of wasted or distorted current costs more when it is produced behind the meter.
| Customer and capacity | Per kWh | How it is charged |
|---|---|---|
| Maximum demand MD1 · 16 to 300 kVA | $0.111 K2.20 | Energy only since 1 November 2025: no kVA demand charge, no fixed charge and no time-of-use. |
| Maximum demand MD2 · 301 to 2,000 kVA | $0.116 K2.30 | The same energy-only structure, one rate for every kWh. |
| Maximum demand MD3 · 2,001 to 5,000 kVA | $0.126 K2.50 | The largest published class, also energy only. |
| Small commercial · up to 15 kVA | $0.033–0.159 K0.66–3.16 | Inclining monthly blocks: 0.66 for the first 100 kWh, 1.35 to 300 kWh, 2.19 to 500 kWh and 3.16 above. |
| Mining and bulk supply above 5,000 kVA | Not published | Large mines buy under bilateral supply agreements, outside the ERB’s published schedule. |
02A Zambian site pays for energy: then pays again for diesel
The grid bill is now simple. The ERB’s decision of October 2025 puts maximum-demand and distribution customers on energy-only tariffs from 1 November 2025: one rate per kWh by capacity band, with no kVA demand charge, no fixed charge and no time-of-use. On top of the grid bill sits a second bill that never appears on a ZESCO statement: the cost of running diesel generators and captive solar through load-shedding. Power quality moves both.
| Line | What it is | Cut by power quality? |
|---|---|---|
| Energy (K/kWh) | One rate by capacity band: K2.20 on MD1 (16 to 300 kVA), K2.30 on MD2 (to 2,000 kVA), K2.50 on MD3 (to 5,000 kVA) | Yes: fewer kWh for the same output |
| Demand and fixed | No kVA demand or fixed charge: both abolished for maximum-demand customers from 1 November 2025 | No line to cut. Correction still frees transformer and backup capacity |
| Power factor | No line in the energy-only tariff; confirm any requirement for your connection with ZESCO | Correction holds power factor at 0.98 or better |
| VAT and excise duty | Added to the bill | Only in proportion to the energy line |
| Diesel and captive-solar backup | Self-generation to bridge load-shedding, outside the ZESCO bill | Yes: fewer kWh to generate, and backup capacity freed for real load |
So the answer to the question Zambian operators now ask: larger sites are no longer billed for kVA, since the ERB moved them to energy-only tariffs, so on the grid bill the saving is the energy line. Poor power factor still costs you, by raising losses and, most expensively in Zambia, by wasting the limited capacity of the diesel generators and inverters you rely on during load-shedding. Both fall as power factor rises towards unity.
03No demand charge to cut: the pull here is commercial
Zambia’s current tariffs give a large site no demand or kVA charge to reduce, and the energy-only schedule has no power-factor line; confirm with ZESCO whether a power-factor requirement applies to your connection. The reason to correct power factor here is therefore mainly commercial: a site with a low power factor draws far more apparent power and reactive current than the same site corrected to 0.98 or better, which wastes transformer headroom, raises losses and, critically during load-shedding, forces an undersized generator or solar-battery system to carry reactive current it could otherwise spend on useful load.
On harmonics and supply quality, the ERB monitors the interconnected system against the Zambian quality-of-supply standard, ZS 387. On site, the rapid spread of variable-speed drives, rectifiers and inverter-based captive solar and batteries is pushing distortion up on weak, genset-fed boards. Holding it in check, so that solar, storage and the existing load can share one board without overheating, increasingly requires active harmonic filtering, not a one-off survey.
04A drought-hit hydro grid, bridged on diesel and solar
One structural force makes power quality a Zambian boardroom issue above all others: load-shedding. Zambia’s power comes mostly from hydro, concentrated on a single, drought-exposed source, Lake Kariba. An El Niño drought, among the worst in Southern Africa in decades, drained much of Kariba’s usable storage. In 2025, the ERB reports, generation averaged 1,488.93 MW against average demand of 2,217.52 MW, a shortfall of 728.59 MW, and load-shedding cost customers 259.5 million hours in January, easing to 123.8 million in December. For a commercial or industrial site, that is not an inconvenience: it is the central operating cost.
Sites responded the only way they could: diesel generators, and a rush into captive solar and batteries. This matters for power quality in two compounding ways. First, the boards these sites now run on are weak, genset- and inverter-fed, so reactive current takes up generator and inverter capacity a site cannot spare. Second, the new solar and battery kit is inverter-based and harmonic-rich, injecting distortion onto those same boards. On the grid supply a site still draws, wasted current shows up as kWh on an energy-only bill. Even with relief as the rains return, the structural exposure, a hydro-dominated system on one drought-prone lake, is unchanged, and the harmonic load from the new inverters persists after the drought.
05Correction and filtering, network-wide
How HarmoniQ fits a site in Zambia
HarmoniQ works on the site’s side of the meter.
At the load
HarmoniQ Alpha
Fitted at each machine, it cleans the current where it is drawn, so every cable upstream carries less of it and runs cooler.
At the drives
HarmoniQ Delta
Fitted at the drives panel, it cleans the current where the drives distort it, before it spreads to the feeder, busbar and transformer.
At the incomer
HarmoniQ Sigma
At the main switchgear, it corrects reactive current where the network meets the grid, so the supply and the meter see cleaner current.
All three are shunt-connected, outside the supply path, and install with zero disruption to production. Together they correct power factor to 0.98 or better across the network, without adding the resonance risk a capacitor bank brings.
Why not just install capacitor banks? Switched-capacitor banks correct power factor in fixed steps at the incoming feed: enough, in theory, to lift power factor at the meter. But on a modern site, with its drives, rectifiers and inverters, they leave most of the problem in place.
The usual answer
Capacitor banks
- Correct power factor in fixed steps, at the incoming feed
- Respond in steps and seconds, so they lag fast-changing loads
- Leave reactive current flowing through your internal network
- On a system carrying harmonics, can form a resonant circuit with the supply, amplifying them
HarmoniQ
Correction across the network
- Corrects continuously, rather than in steps
- Works across the network, where the current is drawn, not at one point
- Corrects power factor to 0.98 or better
- Without adding the resonance risk a capacitor bank brings
06The value is in fuel and freed capacity
On most invoices, three lines fall when the waste stops. In Zambia only one of them is on the bill, energy, because since 1 November 2025 ZESCO has billed its maximum-demand customers on energy alone, with no demand or fixed charge. It is also the line our minimum performance guarantee is written against: kilowatt-hours at the meter, not the bill, which moves with tariffs and charges outside anyone’s control.
- Fewer kilowatt-hours for the same output
- 10–20%
- Power factor across the network
- 0.98+
- Longer equipment life, from cooler cables and transformers
- 2–4×
So in Zambia the saving on the invoice is the energy line. The rest of the value is in plant that runs cooler and lasts longer, and in headroom on the connection you already have. Exhibit 3 sets out where it shows.
| Line | What changes | Effect on the bill |
|---|---|---|
| Energy (kWh) | Wasted current stops turning into heat, so the meter records less | 10–20% fewer kWh for the same output Corrected |
| Harmonics within ZS 387 limits | Lower distortion, cooler transformers and cables | Lower losses, and 2–4× longer equipment life |
Every site’s loads, tariff and reactive profile are different, and the figures above describe the mechanism, not a quote. Our engineers will model the power factor improvement, the energy and fuel saved, the losses reduced and the capacity freed for your specific connection. Get in touch for a site assessment.
07Three steps. Zero disruption.
- Assess Our engineers measure your power factor, reactive energy, harmonics and load profile — on grid, generator and solar — and model the backup capacity and fuel saved and the energy and losses reduced for your site.
- Install Each unit is sized to your site and installed in parallel, where its problem starts — no circuits broken, no production interruption, at sites from agri-processing plants and breweries to retail centres, hospitals and telecom hubs.
- Verify Results are proven at your own meter — switchable on and off so you can confirm the difference in metered results in real time.
08What we hear, and the reality
“Zambian grid power is cheap, so power quality can’t save us much.”
The grid bill is energy alone, but during load-shedding sites run diesel at a cost per kWh well above the grid rate. The case is built on getting more useful work out of that expensive backup, and freeing its capacity for real load, not on the grid tariff.
“We’ve installed solar and batteries, so our power problem is solved.”
Captive solar and storage add generation, but their inverters are harmonic-rich and add distortion to boards already carrying drives and gensets. HarmoniQ removes that distortion and corrects power factor across the network, so less of every kilowatt-hour you generate is wasted.
“Capacitor banks will sort out our power factor.”
Capacitor banks correct in fixed steps at the meter, leave the internal network uncorrected, and can resonate with the harmonics every modern Zambian site now carries. HarmoniQ corrects continuously and network-wide, and filters harmonics, without adding the resonance risk a capacitor bank brings.
Sources
- Energy Regulation Board (ERB), Zambia, Press Statement — Board's Decision on ZESCO's Application to Revise Electricity Tariffs for the Period 1st November 2025 to 31st October 2027 (with Appendix I, Approved ZESCO Tariffs), 31 October 2025; read 8 October 2026.
- ERB, Energy Sector Report 2025, 1 January 2026; read 8 October 2026.
- ERB (copy hosted by ESMAP RISE), Zambian Distribution Grid Code, May 2016 (first issue), 1 May 2016; read 9 October 2026.
Tariffs change. Confirm the rate, surcharge and connection rules that apply to your site with your own utility.


