In brief
- CFE prices large sites by category and by tariff division: energy, by time of day on the GDMTH tariff, plus capacity and distribution charges per kW and a monthly supply charge.
- CFE adds a surcharge to the whole bill below a 0.90 power factor and pays a bonus above it. Since 8 April 2026, medium-voltage sites of 1 MW or more and high-voltage sites are measured against the Grid Code’s 0.97.
- Nearshoring is concentrating new drive-heavy plants in industrial corridors where grid capacity is tight, so headroom on an existing connection is valuable.
- HarmoniQ’s saving is two lines on one invoice: 10–20% fewer kWh and power-factor charges eliminated, proven at your own meter.
Here is what power actually costs in Mexico, how the bill breaks down, and where power quality correction cuts it at sites from nearshoring plants to commercial estates.
01A bill built on demand and power factor, in a nearshoring boom
CFE is Mexico’s basic-supply retailer, billing on regulated tariffs that the Comisión Nacional de Energía authorises for each year and CFE adjusts monthly. A large site is billed on three things: the energy it uses, priced by time of day on the GDMTH tariff for medium-voltage sites of 100 kW and over; the kilowatts of demand it draws, through capacity and distribution charges; and its power factor. Prices differ across CFE’s 17 tariff divisions. For a factory, a cold store or a commercial estate, the unit rate is only part of the story.
So the usual argument that “power is fairly cheap in Mexico, efficiency doesn’t move the needle” misses where the money goes. Every kilowatt of wasted demand is billed through the per-kW charges, and a power factor below the threshold raises the whole bill, every month.
| CFE category | Per kWh | How it is charged |
|---|---|---|
| GDMTH · medium voltage, 100 kW and over | $0.050–0.124 0.902–2.239 MXN | By time of day, from the base period in the cheapest division to the peak in the dearest. On top, a capacity charge and a distribution charge, each per kW a month, and a monthly supply charge. Prices differ across CFE’s 17 tariff divisions, and the generation charges are adjusted every month. |
| GDMTO · medium voltage, under 100 kW | $0.067–0.093 1.20–1.68 MXN | One energy rate, by tariff division. The same per-kW capacity and distribution charges and a supply charge. A GDMTO site that reaches 100 kW is moved to GDMTH. |
| GDBT · low voltage, over 25 kW | $0.072–0.120 1.30–2.16 MXN | One energy rate, by tariff division. A capacity charge and a distribution charge per kW, and a supply charge, by tariff division. |
| Every category · power factor | A surcharge below 90%, a bonus at or above it | A percentage of the whole bill, worked out from the month’s average power factor: the surcharge is capped at 120% and the bonus at 2.5%. Prices are published before VAT (IVA). |
02Energy by time of day, demand per kW, and a power-factor adjustment
The headline peso-per-kWh is only part of the story. A GDMTH site pays for energy, priced differently in the base, intermediate and peak periods; for capacity and distribution, each charged per kW a month; a monthly supply charge; and an adjustment for its power factor. Demand is measured as the highest 15-minute average, but it is billed on the lesser of that peak and the demand implied by the month’s kWh, so a single spike is capped; the capacity charge counts only demand that coincides with the peak period. There is no ratchet, and demand is billed in kW, never kVA.
| Line | What it is | Cut by power quality? |
|---|---|---|
| Energy (kWh, by time of use) | Priced by base, intermediate and peak periods, by tariff division | Yes: fewer kWh for the same output |
| Capacity charge (kW) | Per kW a month, on the lesser of the demand coinciding with the peak period and the demand implied by the month’s kWh | Yes: fewer kW for the same output |
| Distribution charge (kW) | Per kW a month, on the lesser of the month’s maximum demand and the kWh-implied demand | Yes: fewer kW for the same output |
| Supply charge | A fixed monthly charge | No: a fixed charge |
| Power-factor adjustment (factor de potencia) | A percentage of the whole bill: a surcharge below the threshold, a bonus at or above it | Yes: correction clears the surcharge and earns the bonus |
| VAT (IVA) | Added on top; CFE’s prices are published before it | No |
So the answer to two questions Mexican operators often ask: yes, you are billed for demand, per kW through the capacity and distribution charges, and yes, you are billed for poor power factor, through CFE’s adjustment to the whole bill. The surcharge falls away as power factor rises, and the demand charges fall with the kilowatts the waste no longer draws.
03A surcharge below 0.90, and a bar at 0.97 for large sites
Mexico is one of the clearest power-factor regimes anywhere. Under the 2026 tariff, CFE adjusts the whole bill around a 0.90 power factor (factor de potencia), the month’s average. Below it, a surcharge (recargo) of three fifths of (90 ÷ power factor − 1) is added, growing as the factor worsens, up to a cap of 120% of the bill. At or above it, CFE pays a bonus (bonificación) of a quarter of (1 − 90 ÷ power factor), up to 2.5%. Either way, it recurs on every bill.
The bar is higher for large sites. The 2026 tariff sets the surcharge and bonus for medium-voltage sites with contracted demand of 1 MW or more, and for high-voltage sites, against the requirement of the Código de Red, the Grid Code: 0.95 until 8 April 2026, and 0.97 since. On that basis, a large site at 0.95 now pays a surcharge rather than earning a bonus. The Grid Code also asks those sites to hold 0.97 at the connection point for at least 95% of each month, measured in five-minute intervals, a standard a switched bank struggling to track a variable load will routinely miss.
On harmonics, the Grid Code sets current-distortion limits for the same large sites, by the ratio of short-circuit current to load current: at 69 kV and below, total demand distortion from 5.0% on the weakest connections to 20.0% on the strongest, judged on the 95th percentile of ten-minute values over a week. As variable-speed drives, rectifiers, non-linear UPS and behind-the-meter solar multiply across Mexican plants, staying inside those limits increasingly requires active harmonic filtering, not just a one-off survey.
04A nearshoring boom on a capacity-constrained grid
Three structural forces make power quality a Mexican boardroom issue, not just an engineering one. First, the bill structure — already covered: per-kW demand charges, and a power-factor surcharge that is stricter for large sites since April 2026. Second, nearshoring: foreign investment in manufacturing is concentrating new automotive, electronics and aerospace load in Nuevo León, the Bajío and the northern border — all motor- and drive-heavy plants that draw reactive power and inject harmonics. Third, capacity: grid capacity is tight in those same corridors, so freeing transformer and switchgear headroom on the connection you already have is unusually valuable.
The grid is tight as well as busy, and the supply is increasingly inverter-fed. On a grid this stretched, the headroom freed on your own connection is worth as much as the line it takes off the bill.
05Correction and filtering, network-wide
How HarmoniQ fits a site in Mexico
HarmoniQ works across the low-voltage network, where Mexican sites carry their load, where the GDMTH demand and power-factor charges bite, and where the inverter-heavy grid injects distortion.
At the load
HarmoniQ Alpha
Fitted at each machine, it cleans the current where it is drawn, so every cable upstream carries less of it and runs cooler.
At the drives
HarmoniQ Delta
Fitted at the drives panel, it cleans the current where the drives distort it, before it spreads to the feeder, busbar and transformer.
At the incomer
HarmoniQ Sigma
At the main switchgear, it corrects reactive current where the network meets the grid, so the supply and the meter see cleaner current.
All three are shunt-connected, outside the supply path, and install with zero disruption to production. Together they correct power factor to 0.98 or better across the network, without adding the resonance risk a capacitor bank brings.
Why not just install capacitor banks? Switched-capacitor banks correct power factor in fixed steps at the incoming feed: enough, in theory, to lift you over CFE’s threshold at the meter. But on a modern site, with its drives, rectifiers and inverters, they leave most of the problem in place.
The usual answer
Capacitor banks
- Correct power factor in fixed steps, at the incoming feed
- Respond in steps and seconds, so they lag fast-changing loads
- Leave reactive current flowing through your internal network
- On a system carrying harmonics, can form a resonant circuit with the supply, amplifying them
HarmoniQ
Correction across the network
- Corrects continuously, rather than in steps
- Works across the network, where the current is drawn, not at one point
- Corrects power factor to 0.98 or better
- Without adding the resonance risk a capacitor bank brings
06Fewer kWh, fewer kW, no surcharge: where the saving lands
Three lines on the same invoice fall when the waste stops, where the tariff carries them. In Mexico, demand is charged per kW, which power factor correction does not reduce; it falls only in step with the energy saving. The first line is energy, and it is the line our minimum performance guarantee is written against: kilowatt-hours at the meter, not the bill, which also moves with tariffs and charges outside anyone’s control.
- Fewer kilowatt-hours for the same output
- 10–20%
- Power factor, so reactive charges fall away
- 0.98+
- Longer equipment life, from cooler cables and transformers
- 2–4×
Exhibit 3 sets out where each line falls on an invoice in Mexico.
| Line | What changes | Effect on the bill |
|---|---|---|
| Energy (kWh) | Wasted current stops turning into heat, so the meter records less | 10–20% fewer kWh for the same output Corrected |
| Capacity and distribution charges (kW) | Peak real power falls with the losses | Lower kW charges, in step with the energy saving Corrected |
| Power-factor surcharge or bonus (% of the bill) | Power factor corrected to 0.98 or better | The surcharge falls away, and CFE’s bonus applies instead Corrected |
| Harmonics within the Grid Code’s limits | Lower distortion, cooler transformers and cables | Lower losses, and 2–4× longer equipment life |
Every site’s loads, tariff and reactive profile are different, and the figures above describe the mechanism, not a quote. Our engineers will model the energy saved, the power-factor surcharge avoided and bonus earned, the kW charges cut, the losses reduced and the capacity freed for your specific connection. Get in touch for a site assessment.
07Three steps. Zero disruption.
- Assess Our engineers measure your power factor, reactive energy, harmonics and load profile, and model the energy saved, the CFE surcharge avoided and bonus earned, the kW charges cut and the capacity gained for your site, against your tariff division.
- Install Each unit is sized to your site and installed in parallel, where its problem starts — no circuits broken, no production interruption, at sites from nearshoring plants to commercial estates.
- Verify Results are proven at your own meter — switchable on and off so you can confirm the difference in metered results in real time.
08What we hear, and the reality
“Power is fairly cheap in Mexico, so efficiency doesn’t move the needle.”
On the GDMTH tariff the energy rate is only part of the bill: capacity and distribution are charged per kW, and a power factor below 0.90 raises the whole bill. Both are billable today, regardless of the unit price.
“We have capacitor banks, so our power factor is sorted.”
Capacitor banks correct in fixed steps at the meter, leave the internal network uncorrected, and can resonate with the harmonics every modern Mexican plant carries. They also struggle with the Código de Red’s five-minute 0.97 test. HarmoniQ corrects continuously and network-wide, without adding the resonance risk a capacitor bank brings.
“The Código de Red 0.97 rule is a paperwork problem, not an engineering one.”
Since 8 April 2026 the 0.97 factor must hold at the connection point for 95% of each month, in five-minute intervals, and the 2026 tariff measures a large site’s surcharge against it. A site at 0.95 falls short on both. Dynamic correction is what actually meets the standard.
Sources
- Comisión Nacional de Energía (CNE), published by CFE in the Diario Oficial de la Federación, ACUERDO por el que la Comisión Nacional de Energía autoriza el cálculo y ajuste de las tarifas finales del suministro básico que debe aplicar de manera individual a la Comisión Federal de Electricidad … del 01 de enero al 31 de diciembre de 2026 (Acuerdo CT/11.SE/8-2025), 1 April 2026; read 8 October 2026.
- Comisión Federal de Electricidad, Diario Oficial de la Federación (by order of the Comisión Nacional de Energía), TARIFAS Finales del Suministro Básico que deberá aplicar la Comisión Federal de Electricidad, en la modalidad de Suministradora de Servicios Básicos a sus usuarios, a partir del 1 de septiembre de 2026 (oficio CNE F00.06.UE, Anexo II), 30 September 2026; read 9 October 2026.
- Comisión Reguladora de Energía, Diario Oficial de la Federación, RESOLUCIÓN Núm. RES/550/2021 … Código de Red (Manual Regulatorio de Requerimientos Técnicos para la Conexión de Centros de Carga), 31 December 2021; read 8 October 2026.
Tariffs change. Confirm the rate, surcharge and connection rules that apply to your site with your own utility.


