In brief
- Since July 2025, TNB’s tariff in Peninsular Malaysia splits the bill into energy, capacity, network and retail charges, with base rates fixed to the end of 2027 and a monthly fuel adjustment on top.
- A medium-voltage site pays 29.83 sen per kWh and RM89.27 per kW of monthly maximum demand; below 0.85 power factor, TNB adds 1.5% of the energy, demand and fuel charges for every 0.01 short.
- Electrical and electronics plants carry heavy harmonic loads, and a surge of data-centre demand in Johor is making grid capacity scarce.
- HarmoniQ’s saving is two lines on one invoice: 10–20% fewer kWh and power-factor charges eliminated, proven at your own meter.
Here is what power actually costs in Malaysia, how the bill breaks down, and where power quality correction cuts it at sites from E&E plants to commercial estates.
01A restructured tariff, fixed to 2027
For years Malaysian power was cheap and simple. That changed on 1 July 2025, when the Energy Commission (Suruhanjaya Tenaga) restructured the tariff for Peninsular Malaysia for the regulatory period to 31 December 2027 (RP4). Non-domestic customers are now classed by supply voltage, and the bill is split into energy, capacity, network and retail charges, with a monthly fuel adjustment layered on top. A medium-voltage site on the general tariff pays 29.83 sen per kWh for energy, about $0.073, and RM89.27 per kW of monthly maximum demand for capacity and network. A low-voltage site pays all of it per kWh: 50.68 sen before the fuel adjustment and tax. Sabah and Sarawak run their own tariffs.
So the old assumption that “Malaysian industrial power is cheap, efficiency doesn’t move the needle” no longer holds. At medium and high voltage, every percentage point of wasted current shows up in the energy line and the maximum-demand line at once, and a poor power factor adds a surcharge on both.
| Supply and tariff | Per kWh | How it is charged |
|---|---|---|
| Low voltage · general | $0.124 50.68 sen | Every charge per kWh, with no kW charge: energy 27.03 sen, capacity 8.83 and network 14.82. Plus RM20 a month retail. |
| Medium voltage · general | $0.073 29.83 sen | Energy per kWh, plus RM29.43 capacity and RM59.84 network per kW of monthly maximum demand, RM89.27 in all, and RM200 a month retail. |
| Medium voltage · time of use | $0.067–0.077 27.23–31.32 sen | 31.32 sen from 14:00 to 22:00 on weekdays, 27.23 off-peak and all weekend. RM97.06 per kW of peak-period maximum demand; off-peak demand is not charged. |
| High voltage · general | $0.105 43.03 sen | Plus RM31.21 per kW of monthly maximum demand (16.68 capacity, 14.53 network) and RM250 a month retail. |
| High voltage · time of use | $0.099–0.109 40.43–44.52 sen | 44.52 sen at peak, 40.43 off-peak, plus RM44.82 per kW of peak-period maximum demand. |
02A Malaysian industrial bill is more than the energy you use
The headline sen-per-kWh is only part of the story. Under RP4, a medium- or high-voltage site pays its capacity and network charges per kW of its monthly maximum demand: together they are the demand charge, with no separate one on top. At low voltage both are billed per kWh, and there is no kW charge at all. Every site pays a monthly fuel adjustment and, critically for power quality, a power-factor surcharge if its power factor falls too low.
| Line | What it is | Cut by power quality? |
|---|---|---|
| Energy (kWh) | Per kWh, with peak and off-peak rates on the time-of-use tariffs | Yes: fewer kWh for the same output |
| Capacity and network, medium and high voltage (RM/kW) | Per kW of monthly maximum demand: RM89.27 on medium-voltage general, RM97.06 on peak-period demand for time of use, RM31.21 to RM44.82 at high voltage | Yes: fewer kW drawn for the same output |
| Capacity and network, low voltage | Per kWh: 8.83 and 14.82 sen | Yes: they fall with every kWh saved |
| Retail charge | A fixed monthly charge, RM20 to RM250 by voltage | No |
| Automatic Fuel Adjustment | Set monthly, as a rebate or surcharge per kWh; TNB’s bill calculator applies 3.61 sen for October 2026 | Yes: it falls with the units saved |
| Power-factor surcharge | Below 132 kV: 1.5% of the energy, demand and fuel charges for every 0.01 below 0.85, and 3% for every 0.01 below 0.75 | Yes: power factor correction removes it |
| Service tax and renewable-energy levy | Percentages added to the bill | Only as far as the bill they apply to falls |
So the answer to two questions Malaysian operators often ask: yes, you are billed for demand at medium and high voltage, through the capacity and network charges per kW; and yes, you are billed for poor power factor, through TNB’s power-factor surcharge. Both fall when the waste stops: the surcharge as power factor rises towards unity, the demand charge as fewer kW are drawn for the same output. A related trap is the Connected Load Charge: on a new or upgraded medium- or high-voltage connection, TNB bills RM8.50 per kW of shortfall when actual maximum demand stays below a set share of the demand the site declared, so demand has to be declared and managed, not just minimised.
03A surcharge below 0.85, and harmonics held to planning levels
Malaysia imposes an explicit power-factor penalty. TNB requires a monthly average power factor of at least 0.85 for supplies below 132 kV, and 0.90 at 132 kV and above, and applies a surcharge when a site falls short. Below 132 kV it is 1.5% of the energy, demand and fuel charges for every 0.01 below 0.85, rising to 3% for every 0.01 below 0.75. There is no credit for bettering the threshold. A motor- and drive-heavy plant that drifts below 0.85 therefore pays a recurring penalty on top of its energy and demand charges, a penalty that disappears the moment it is corrected to 0.98+.
On harmonics, TNB’s Electricity Supply Application Handbook sets voltage distortion planning levels by the UK’s Engineering Recommendation G5/4: total harmonic distortion of 5% at 400 V, 4% at 11 to 22 kV and 3% at 33 kV and 132 kV. It declares its supply environment by IEC 61000-2-4. As variable-speed drives, rectifiers, non-linear UPS and behind-the-meter solar multiply on Malaysian sites, staying inside those levels increasingly requires active harmonic filtering, not just a one-off survey.
04An E&E powerhouse facing a data-centre surge
Three structural forces make power quality a Malaysian boardroom issue, not just an engineering one. First, the tariff, already covered: newly restructured, with explicit demand and power-factor charges. Second, the E&E base: electrical and electronics is Malaysia’s largest export sector, and the country is one of the world’s main centres for back-end semiconductor work: precision plant dense with the drives, rectifiers and power supplies that inject harmonics. Third, the data-centre surge: Johor has become one of South-East Asia’s fastest-growing data-centre hubs, with analysts projecting data centres to take a large share of the state’s electricity — a wave of new, inverter-heavy, capacity-hungry load arriving on the grid at once.
What matters less in Malaysia is day-to-day resilience: the grid is reliable, and interruptions per customer are rare. So unlike sites in parts of Africa or the Gulf, Malaysian operators are driven by cost, the new demand and power-factor charges, harmonic compliance and scarce grid capacity — rather than by keeping the lights on.
05Correction and filtering, network-wide
How HarmoniQ fits a site in Malaysia
HarmoniQ works across the low-voltage network, where Malaysian sites carry their cost, where the maximum-demand charge and power-factor surcharge bite, and where E&E lines inject distortion.
At the load
HarmoniQ Alpha
Fitted at each machine, it cleans the current where it is drawn, so every cable upstream carries less of it and runs cooler.
At the drives
HarmoniQ Delta
Fitted at the drives panel, it cleans the current where the drives distort it, before it spreads to the feeder, busbar and transformer.
At the incomer
HarmoniQ Sigma
At the main switchgear, it corrects reactive current where the network meets the grid, so the supply and the meter see cleaner current.
All three are shunt-connected, outside the supply path, and install with zero disruption to production. Together they correct power factor to 0.98 or better across the network, without adding the resonance risk a capacitor bank brings.
Why not just install capacitor banks? Switched-capacitor banks correct power factor in fixed steps at the incoming feed: enough, in theory, to lift you over the 0.85 surcharge threshold at the meter. But on a modern site, with its drives, rectifiers and inverters, they leave most of the problem in place.
The usual answer
Capacitor banks
- Correct power factor in fixed steps, at the incoming feed
- Respond in steps and seconds, so they lag fast-changing loads
- Leave reactive current flowing through your internal network
- On a system carrying harmonics, can form a resonant circuit with the supply, amplifying them
HarmoniQ
Correction across the network
- Corrects continuously, rather than in steps
- Works across the network, where the current is drawn, not at one point
- Corrects power factor to 0.98 or better
- Without adding the resonance risk a capacitor bank brings
06Higher tariff, a real surcharge: the savings compound
Three lines on the same invoice fall when the waste stops, where the tariff carries them. In Malaysia, demand is charged per kW, which power factor correction does not reduce; it falls only in step with the energy saving. The first line is energy, and it is the line our minimum performance guarantee is written against: kilowatt-hours at the meter, not the bill, which also moves with tariffs and charges outside anyone’s control.
- Fewer kilowatt-hours for the same output
- 10–20%
- Power factor, so reactive charges fall away
- 0.98+
- Longer equipment life, from cooler cables and transformers
- 2–4×
Exhibit 3 sets out where each line falls on an invoice in Malaysia.
| Line | What changes | Effect on the bill |
|---|---|---|
| Energy (kWh) | Wasted current stops turning into heat, so the meter records less | 10–20% fewer kWh for the same output Corrected |
| Demand charge (kW), medium and high voltage | Peak real power falls with the losses | Lower kW demand charge, in step with the energy saving Corrected |
| Power-factor charge | Power factor corrected to 0.98 or better | Falls away where it applies Corrected |
| Harmonics within TNB’s planning levels | Lower distortion, cooler transformers and cables | Lower losses, and 2–4× longer equipment life |
Every site’s loads, tariff and reactive profile are different, and the figures above describe the mechanism, not a quote. Our engineers will model the power factor improvement, power-factor surcharge avoided, maximum demand and losses reduced and capacity freed for your specific connection. Get in touch for a site assessment.
07Three steps. Zero disruption.
- Assess Our engineers measure your power factor, harmonics, maximum demand and load profile, and model the power-factor surcharge avoided, maximum demand and losses reduced and capacity gained for your site.
- Install Each unit is sized to your site and installed in parallel, where its problem starts — no circuits broken, no production interruption, at sites from E&E and semiconductor plants to commercial estates.
- Verify Results are proven at your own meter — switchable on and off so you can confirm the difference in metered results in real time.
08What we hear, and the reality
“Malaysian power is cheap, so efficiency barely matters.”
The July 2025 restructuring unbundled the bill into energy, capacity, network and retail charges and added a monthly fuel adjustment; at medium and high voltage, capacity and network are charged per kW of maximum demand, and every site faces a power-factor surcharge. Every wasted unit, and every demand spike, is now charged more visibly than before.
“We have capacitor banks, so our power factor is sorted.”
Capacitor banks correct in fixed steps at the meter, leave the internal network uncorrected, and can resonate with the harmonics every modern Malaysian E&E plant carries. HarmoniQ corrects continuously and network-wide, without adding the resonance risk a capacitor bank brings.
“The power-factor surcharge is too small to bother with.”
TNB adds 1.5% of the energy, demand and fuel charges for every 0.01 below 0.85 power factor, and motor- and drive-heavy sites often sit below it. Correcting to 0.98+ removes that recurring surcharge and, at medium and high voltage, the lower losses trim your maximum-demand (kW) charge at the same time.
Sources
- Suruhanjaya Tenaga (Energy Commission), Jadual Elektrik Baharu: Lebih 23.6 Juta Pengguna Domestik Semenanjung Nikmati Kadar Lebih Adil (press release, 20 June 2025), 20 June 2025; read 8 October 2026.
- Tenaga Nasional Berhad, Bursa announcement GA1-20062025-00054: Implementation of RP4 Revised Electricity Tariff Schedule for Peninsular Malaysia, 23 June 2025; read 8 October 2026.
- Suruhanjaya Tenaga (Energy Commission), myEnergyStats portal, Jadual Tarif Elektrik di Semenanjung Bagi Tempoh 1 Julai 2025 Hingga 31 Disember 2027, 9 July 2025; read 8 October 2026.
- TNB (myTNB), Understand Your Electricity Tariff (RP4 tariff restructuring page); read 8 October 2026.
- TNB (myTNB), myTNB bill calculator rate table (js/rates.js); read 8 October 2026.
- Tenaga Nasional Berhad (TNB), Charges & Penalties — Power Factor Surcharge; Connected Load Charge; read 8 October 2026.
- Tenaga Nasional Berhad, Electricity Supply Application Handbook (ESAH), Version 3.1, 1 January 2022; read 8 October 2026.
Tariffs change. Confirm the rate, surcharge and connection rules that apply to your site with your own utility.


