In brief
- Edenor’s large users around Buenos Aires paid 132.55 to 164.46 pesos per kWh of energy in September 2026, before taxes, plus capacity charges per kW. Provincial distributors set their own tariffs.
- ENRE raised the minimum power factor for Edenor and Edesur customers to cos φ 0.95. Between 0.85 and 0.95 the surcharge applies at 10% of its value for now; below 0.85 it applies in full.
- Beyond the tariff, a growing inverter share raises harmonic distortion at commercial sites, and a stretched grid makes headroom on an existing connection valuable.
- HarmoniQ’s saving is two lines on one invoice: 10–20% fewer kWh and power-factor charges eliminated, proven at your own meter.
Here is what power actually costs in Argentina, how the bill breaks down, and where power quality correction cuts it at sites from manufacturing plants to commercial estates.
01A tariff set monthly, by distributor, as the subsidies come off
Argentine electricity was long held down by subsidies, and that era is ending for business users. Around Buenos Aires (AMBA), Edenor and Edesur are regulated nationally; elsewhere, provincial distributors set their own tariffs. Edenor’s chart, set monthly, charged its large users (Tarifa 3, 50 kW and over) 132.55 to 164.46 pesos per kWh of energy in September 2026, about $0.087 to $0.108 before taxes, by voltage and time of day, with capacity charged on top. For a factory, a cold store or a commercial estate, the price of a kilowatt-hour is reason enough to stop wasting any.
The relief that still cushions bills is aimed at households, not at commercial and industrial sites, so the argument that “Argentine power is cheap, efficiency doesn’t move the needle” no longer holds. Every percentage point of wasted current is charged at the energy rate, and the capacity a site draws is charged per kW on top.
| Edenor tariff | Energy per kWh | How it is charged |
|---|---|---|
| Tarifa 3 · medium voltage, 50 kW and over | $0.087–0.103 132.55–156.30 ARS | Energy by period (peak, rest and off-peak) across the chart’s two size bands, plus capacity per kW a month: 9,428.50 pesos contracted and 11,315.80 drawn. |
| Tarifa 3 · low voltage, 50 kW and over | $0.096–0.108 144.97–164.46 ARS | Peak energy across the two size bands, plus capacity at 19,939.19 pesos per kW contracted and 10,306.30 drawn, and a monthly fixed charge of 189,126.46 pesos in the smaller band. |
| Tarifa 2 · 10 to 50 kW | $0.093 141.25 ARS | One energy rate, plus capacity at 22,371.59 pesos per kW contracted and 9,818.37 drawn. |
| Tarifa 1-G · small commercial, up to 10 kW | $0.177–0.195 267.92–296.33 ARS | Energy by monthly consumption block, from the first 800 kWh to above 2,000 kWh, with no capacity charge. |
02Energy by period, capacity per kW, and a power-factor surcharge
The headline price per kWh is only part of the story. On Edenor’s Tarifa 3, a site pays a monthly fixed charge; energy by period (peak, rest and off-peak); and two capacity charges per kW: one on the capacity it contracts, a 15-minute average agreed for 12 months at a time, and one on the capacity it actually draws. At medium voltage in September 2026 those were 9,428.50 and 11,315.80 pesos per kW a month. A demand above the contracted capacity becomes the new contracted capacity for the next 6 months. Below the regulated minimum power factor, a surcharge is added.
| Line | What it is | Cut by power quality? |
|---|---|---|
| Energy (kWh, by period) | Peak, rest and off-peak rates per kWh, by voltage | Yes: fewer kWh for the same output |
| Contracted capacity (Potencia Contratada, kW) | Per kW a month on the capacity agreed for 12 months; a higher demand resets it for the next 6 | Yes, at renewal: fewer kW for the same output |
| Drawn capacity (Potencia Adquirida, kW) | Per kW a month on the capacity actually drawn | Yes: fewer kW drawn for the same output |
| Fixed charge | A monthly charge: 189,126.46 pesos for a low-voltage Tarifa 3 site in the smaller band | No: a fixed charge |
| Power-factor surcharge (recargo) | Added when cos φ falls below 0.95: between 0.85 and 0.95 at 10% of its value for now; all reactive surcharges capped at 40% of the month’s net charges | Yes: power factor correction removes it |
| Taxes | Added to the chart’s prices | No |
So the answer to two questions Argentine operators often ask: yes, you are billed for capacity (potencia), per kW contracted and drawn, never per kVA, and yes, you are billed for poor power factor, through the surcharge below cos φ 0.95. The surcharge falls away as power factor rises, and the capacity charges fall as fewer kW are drawn for the same output.
03A cos φ 0.95 minimum, with the surcharge phased in
Argentina penalises low power factor explicitly. In Resolución 628/2024, the national regulator raised the minimum power factor for Edenor and Edesur customers from 0.85 to 0.95 and authorised a surcharge for excess reactive energy below it. The phase-in has since been slowed: under Resolución 76/2025, the surcharge between 0.85 and 0.95 has applied at 10% of its full value since 1 October 2024, and ENRE is to raise it in steps; below 0.85, the original surcharge applies in full. All reactive surcharges together are capped at 40% of the month’s net charges before taxes, and below a cos φ of 0.60 the distributor may suspend supply. Under the original concession rules, a large user’s surcharge was 1.5% of the energy charge for each 0.01 that tan φ exceeded 0.62. A motor- and drive-heavy plant below 0.95 therefore pays a recurring surcharge that disappears once power factor is corrected to 0.98 or better.
On harmonics, your distributor sets the limits on what a site’s load may emit, so confirm them when you connect or extend. As variable-speed drives, rectifiers, non-linear UPS and behind-the-meter solar multiply on Argentine sites, keeping distortion low increasingly requires active harmonic filtering, not just a one-off survey.
04Rising tariffs, a high-inverter mix, and a strained grid
Three structural forces make power quality an Argentine boardroom issue, not just an engineering one. First, the tariff: already covered, reset every month as subsidies are withdrawn, with a power-factor surcharge that ENRE is to raise in steps. Second, the generation mix: gas-fired thermal supplies the largest share of generation, alongside hydro and a fast-growing inverter-based segment — wind and solar climbing — and that rising inverter share raises harmonic distortion and reactive-power volatility at commercial and industrial sites. Third, a strained grid: years of frozen tariffs and under-investment have left transmission and distribution stretched, so freeing transformer and switchgear headroom on the connection you already have, while cutting the current you draw, is unusually valuable.
Resilience matters at summer peaks, but for most commercial and industrial operators the day-to-day driver is cost: the energy rate, the capacity charges and the power-factor surcharge.
05Correction and filtering, network-wide
How HarmoniQ fits a site in Argentina
HarmoniQ works across the low-voltage network, where Argentine sites carry their cost, where the cos φ 0.95 surcharge and the potencia charge bite, and where the inverter-heavy grid injects distortion.
At the load
HarmoniQ Alpha
Fitted at each machine, it cleans the current where it is drawn, so every cable upstream carries less of it and runs cooler.
At the drives
HarmoniQ Delta
Fitted at the drives panel, it cleans the current where the drives distort it, before it spreads to the feeder, busbar and transformer.
At the incomer
HarmoniQ Sigma
At the main switchgear, it corrects reactive current where the network meets the grid, so the supply and the meter see cleaner current.
All three are shunt-connected, outside the supply path, and install with zero disruption to production. Together they correct power factor to 0.98 or better across the network, without adding the resonance risk a capacitor bank brings.
Why not just install capacitor banks? Switched-capacitor banks correct power factor in fixed steps at the incoming feed: enough, in theory, to lift you over the cos φ 0.95 threshold at the meter. But on a modern site, with its drives, rectifiers and inverters, they leave most of the problem in place.
The usual answer
Capacitor banks
- Correct power factor in fixed steps, at the incoming feed
- Respond in steps and seconds, so they lag fast-changing loads
- Leave reactive current flowing through your internal network
- On a system carrying harmonics, can form a resonant circuit with the supply, amplifying them
HarmoniQ
Correction across the network
- Corrects continuously, rather than in steps
- Works across the network, where the current is drawn, not at one point
- Corrects power factor to 0.98 or better
- Without adding the resonance risk a capacitor bank brings
06Fewer kWh, fewer kW, no surcharge: where the saving lands
Three lines on the same invoice fall when the waste stops, where the tariff carries them. In Argentina, demand is charged per kW, which power factor correction does not reduce; it falls only in step with the energy saving. The first line is energy, and it is the line our minimum performance guarantee is written against: kilowatt-hours at the meter, not the bill, which also moves with tariffs and charges outside anyone’s control.
- Fewer kilowatt-hours for the same output
- 10–20%
- Power factor, so reactive charges fall away
- 0.98+
- Longer equipment life, from cooler cables and transformers
- 2–4×
Exhibit 3 sets out where each line falls on an invoice in Argentina.
| Line | What changes | Effect on the bill |
|---|---|---|
| Energy (kWh) | Wasted current stops turning into heat, so the meter records less | 10–20% fewer kWh for the same output Corrected |
| Capacity charges (kW contracted and drawn) | Peak real power falls with the losses | Lower drawn kW at once, and a lower contracted capacity at renewal Corrected |
| Power-factor surcharge (below cos φ 0.95) | Power factor corrected to 0.98 or better | Falls away Corrected |
| Harmonics within your distributor’s limits | Lower distortion, cooler transformers and cables | Lower losses, and 2–4× longer equipment life |
Every site’s loads, tariff and reactive profile are different, and the figures above describe the mechanism, not a quote. Our engineers will model the power factor improvement, the recargo and potencia charges avoided, losses reduced and capacity freed for your specific connection. Get in touch for a site assessment.
07Three steps. Zero disruption.
- Assess Our engineers measure your power factor, reactive energy, harmonics and load profile, and model the recargo por factor de potencia and potencia charges avoided, losses reduced and capacity gained for your site.
- Install Each unit is sized to your site and installed in parallel, where its problem starts — no circuits broken, no production interruption, at sites from manufacturing plants to commercial estates.
- Verify Results are proven at your own meter — switchable on and off so you can confirm the difference in metered results in real time.
08What we hear, and the reality
“Argentine power is subsidised and cheap, so efficiency barely matters.”
The subsidies are being withdrawn, and the relief that remains is aimed at households. Business users pay close to the full cost of supply, every kWh and every kW of it.
“We have capacitor banks, so our power factor is sorted.”
Capacitor banks correct in fixed steps at the meter, leave the internal network uncorrected, and can resonate with the harmonics every modern Argentine site carries. HarmoniQ corrects continuously and network-wide, without adding the resonance risk a capacitor bank brings.
“The power-factor surcharge is too small to bother with.”
Between 0.85 and 0.95 it applies at 10% of its value for now, but ENRE is to raise it in steps, and below 0.85 it applies in full, up to 40% of the month’s net charges. Correcting to 0.98 or better removes it, and the lower losses trim your capacity charges at the same time.
Sources
- Ente Nacional Regulador del Gas y la Electricidad, published in InfoLEG, Cuadro Tarifario vigencia a partir del 1° de septiembre de 2026 — EDENOR (IF-2026-83508344-APN-UARYEE#ENREGE), 28 August 2026; read 8 October 2026.
- Ente Nacional Regulador de la Electricidad, Boletín Oficial, Resolución ENRE 628/2024 — Programa para la Mejora del Factor de Potencia (Edenor and Edesur), 11 September 2024; read 8 October 2026.
- ENRE (Biblioteca ENRE), Contrato de Concesión EDENOR S.A. — Subanexo 1, Régimen Tarifario: Capítulos 1–3 (Tarifas 1, 2 y 3), 1 May 1992; read 8 October 2026.
- Ente Nacional Regulador de la Electricidad, Boletín Oficial, Resolución ENRE 628/2024, Anexo I (IF-2024-97600218-APN-ARYEE#ENRE) — Subanexo 1, Régimen Tarifario: new power-factor incisos for Tarifas 1, 2 and 3, 11 September 2024; read 9 October 2026.
- Ente Nacional Regulador de la Electricidad, Boletín Oficial, Resolución ENRE 76/2025 — modifies Res. 628/2024 (phase-in of the 0.85–0.95 surcharge), 29 January 2025; read 8 October 2026.
Tariffs change. Confirm the rate, surcharge and connection rules that apply to your site with your own utility.


